DCMA Manual 2101-01
Acceptance
==========================================================
Office of Primary
Responsibility Product Acceptance and Proper Payment Capability
Effective: March 24, 2019
Releasability: Cleared for public release
Implements: DCMA-INST 2101, "Product Acceptance and Proper Payments,”
February 14, 2019
Incorporates and Cancels: DCMA-INST 302, “First Article and Production Lot Testing,”
December 17, 2013
DCMA-INST 310, “Inspection Stamping,” May 02, 2013
DCMA-INST 312, “Standard Inspection Requirements” May 15,
2013
DCMA INST 314, “Product Acceptance & Release,” January 07,
2013
Internal Control: Process flow key control are on the Resource Page
Labor Codes: Located on the Resource Page
Resource Page Link: https://360.dcma.mil/sites/policy/PA/SitePages/2101-01r.aspx
Approved by: David H. Lewis, VADM, USN, Director
__________________________________________________________________
Purpose: This issuance, in accordance with the authority in DoD Directive 5105.64, implements
policy, assigns responsibilities, and provides procedures for:
Surveillance activities for First Article and Production Lot Testing when contractually
required
DCMA-MAN 2101-01, March 24, 2019
2
Inspection Stamping as requested by the customer where a chain of custody is required
Standard Inspection Requirements verifying the contractor’s inspection system is
acceptable to the Government
Product Acceptance & Release when all contractual requirements are met
DCMA-MAN 2101-01, March 24, 2019
TABLE OF CONTENTS 3
TABLE OF CONTENTS
SECTION 1: GENERAL ISSUANCE INFORMATION ..........................................................5
1.1. Applicability .......................................................................................................................5
1.2. Policy .................................................................................................................................5
SECTION 2: RESPONSIBILITIES ............................................................................................6
2.1. Capability Manager, Product Acceptance and Proper Payment .........................................6
2.2. Performance Advocacy Enterprise .....................................................................................6
2.3. Operational Unit Directorate..............................................................................................6
2.4. Contract Management Office Commander/Director .........................................................7
2.5. Contract Management Office Functional Director, Contracts, Quality Assurance,
Engineering and Manufacturing .......................................................................................7
2.6. First Level Supervisor .......................................................................................................7
2.7. Administrative Contracting Officer ...................................................................................8
2.8. Functional Specialist .........................................................................................................8
2.9. Contract Management Office Inspection Stamp Custodian ...............................................9
2.10. Inspection Stamp Custodian Operational Unit Directorate ..............................................9
SECTION 3: FIRST ARTICLE AND PRODUCTION LOT TESTING ............................... 10
3.1. Contract Receipt and Review ........................................................................................... 10
3.2. Functional Specialist Assistance for Software ................................................................. 10
3.3. Participate in Postaward Orientation Conference or Hold a Functional Specialist ..........
Meeting ............................................................................................................................ 10
3.4. Develop First Article Test and/or Production Lot Test Surveillance Plan or Update the
Current Contractor Facility or Program Surveillance Plan ............................................... 11
3.5. Government Surveillance Hold Points ............................................................................. 11
3.6. Determine Need for Government Surveillance at Subcontractor Level ........................... 12
3.7. Execute First Article Test and/or Production Lot Test Surveillance Plan ........................ 12
3.8. Notify Administrative Contracting Officer and Procuring Contracting Officer of Any
Nonconformance(s), or Request(s) for Variance and Request Instructions ...................... 12
3.9. Document First Article Test and/or Production Lot Test Results ..................................... 12
3.10. First Article Test and/or Production Lot Test Approval ................................................. 13
3.11. First Article Test and/or Production Lot Test Unit Shipment ......................................... 14
3.12. Records Management ..................................................................................................... 14
SECTION 4: INSPECTION STAMPING ................................................................................ 15
4.1. Inspection Stamps ............................................................................................................15
SECTION 5: STANDARD INSPECTION REQUIREMENTS .............................................. 16
5.1. Determining the Acceptability of the Contractor’s Inspection System ............................ 16
5.2. Assess the Contractor’s Inspection System ...................................................................... 16
5.3. Document the Results of Inspection System Review ....................................................... 18
5.4. Issue Corrective Action Request ..................................................................................... .19
SECTION 6: PRODUCT ACCEPTANCE AND RELEASE .................................................. 20
6.1. Authorized Personnel Performing Acceptance ................................................................. 20
6.2. Acceptor Authorization .................................................................................................... 21
6.3. Prior to Acceptance .......................................................................................................... 21
DCMA-MAN 2101-01, March 24, 2019
TABLE OF CONTENTS 4
6.4. Government Contract Surveillance .................................................................................. 21
6.5. Authorize Shipment of Supplies ....................................................................................... 22
6.6. Product Acceptance Document Sampling ........................................................................ 24
6.7. Verifying Product Acceptance Documents ...................................................................... 24
6.8. Process Corrected Acceptance Documents ...................................................................... 26
6.9. Process a Replacement Acceptance Document. ............................................................... 26
6.10. Financial Improvement Audit Readiness Guidance ....................................................... 26
GLOSSARY .................................................................................................................................. 27
G.1. Definitions ....................................................................................................................... 27
G.2. Acronyms ........................................................................................................................ 29
REFERENCES ............................................................................................................................. 31
DCMA-MAN 2101-01, March 24, 2019
SECTION 1: GENERAL ISSUANCE INFORMATION 5
SECTION 1: GENERAL ISSUANCE INFORMATION
1.1. APPLICABILITY.
a. This Manual applies to all DCMA personnel performing administration and/or
surveillance activities leading up to and including acceptance unless higher-level regulations,
policy, guidance, or agreements take precedence. DCMA functional elements having unique
surveillance requirements must maintain and follow their supplemental instructions that meet the
intent of this Manual. Oversight and administration of highly sensitive, classified, cryptologic,
and intelligence projects and programs must follow this Manual to the extent practicable.
b. In some instances, federal regulations and DoD Issuances (e.g., Federal Acquisition
Regulation (FAR) 46.406, “Foreign Governments,Defense Federal Acquisition Regulation
Supplement (DFARS) 225.870, “Contracting with Canadian Contractors,” DFARS Procedures,
Guidance and Information (PGI) 225.8, “Other International Agreements and Coordination”) and
Host Nation or Memorandum of Agreements, expressly state the processes of inspection and
acceptance are performed by other agencies for certain commodities. This requirement remains
in force regardless of whether there are full or partial contract administration responsibilities.
c. FAR 46.408, “Single-Agency Assignments of Government Contract Quality Assurance,
requires Government-wide responsibility for quality assurance (QA) support for acquisitions of
certain commodities assigned as follows:
(1) For drugs, biologics, and other medical supplies - the Food and Drug
Administration.
(2) For food, except seafood - the Department of Agriculture.
(3) For seafood the National Marine Fisheries Service of the Department of
Commerce.
1.2. POLICY. It is DCMA policy when Acceptance is delegated to DCMA, that only
authorized personnel accept supplies/services tendered for acceptance by the contractor when
there is a basis of confidence that the supplies/services conform to contract requirements. It is
also DCMA policy to execute this manual in a safe, efficient, effective, and ethical manner.
Contractor submitted creditable objective evidence of technical conformance will be used as a
basis for product acceptance. Credible of that evidence will be determined based upon review of
DCMA surveillance activities results.
DCMA-MAN 2101-01, March 24, 2019
SECTION 2: RESPONSIBILITIES 6
SECTION 2: RESPONSIBILITIES
2.1. CAPABILITY MANAGER, PRODUCT ACCEPTANCE AND PROPER PAYMENT.
The Capability Manager will:
a. Serve as approval authority for waiver/deviation requests to this Manual.
b. Oversee the development, implementation, administration, and management of this
Manual.
2.2. PERFORMANCE ADVOCACY ENTERPRISE. The Enterprise Performance Advocacy
(DCMA-TDA) Director will:
a. Exercise staff supervision of this Manual by engaging DCMA Operational Units for
oversight and assistance, coordinating technical support for internal and external audits,
improving operational efficiencies, and supporting data collection and analysis for decision
making and requirements development across the Agency.
b. Process waiver/deviation requests for this Manual providing technical recommendations
to the Product Acceptance and Proper Payment Capability Manager.
c. Assist DCMA Technical Directorate Manufacturing and Quality (DCMA-TDM) stamp
custodian with assigning and distributing stamps to the Operational Unit Directorate (OUD).
d. Assist DCMA-TDM stamp custodian with verifying Agency stamp inventory levels
annually.
2.3. OPERATIONAL UNIT DIRECTORATE. The OUD Commander will ensure their
directorate:
a. Assists CMOs with deleting Aging Receiving Reports (RR) and Repairables Receiving
Reports (RRR).
b. Runs Management Reporting System monthly reports and provides to the CMOs.
c. Notifies DCMA-TDM quarterly of the status of the Aging RR/RRR.
d. Notifies DCMA-TDM when issue with cleanup of the Aging RR/RRR are not within the
CMOs and/or OUDs area of responsibility.
e. Maintains an inventory of inspection stamps on hand for issuance to the Contract
Management Office(s) (CMOs) when needed.
f. Adjudicate CMO requests for new inspection stamps based on criteria outlined in Section
4 of this Manual and the Guidebook on the Resource Page of this Manual.
DCMA-MAN 2101-01, March 24, 2019
SECTION 2: RESPONSIBILITIES 7
g. Completes an inventory of all stamps on an annual basis and when tasked by a DCMA
Headquarters tasking memorandum.
h. Notifies DCMA-TDM point of contact when inventories are completed.
2.4. CONTRACT MANAGEMENT OFFICE COMMANDER/DIRECTOR. The CMO
Commander or Director will ensure:
a. The CMO complies with the requirements of this Manual.
b. Appropriate and adequate resources are in place to execute the requirements.
2.5. CONTRACT MANAGEMENT OFFICE FUNCTIONAL DIRECTOR,
CONTRACTS, QUALITY ASSURANCE, ENGINEERING AND MANUFACTURING.
The Directors:
a. Will implement this Manual and applicable DOD requirements within their respective
function and CMO. The respective Functional Director will serve as the focal point for:
(1) Applicable internal and external performance measures.
(2) The development of Standard Operating Procedures that augment this Manual under
their purview to ensure these procedures are consistently applied throughout the CMO’s
functional community.
b. Ensure Aging RR/RRR are processed accordingly or the contractor is contacted to have
them deleted, voided and/or validated as current.
2.6. FIRST LEVEL SUPERVISOR. The First Level Supervisor (FLS) will:
a. Ensure their respective FS possess the necessary competencies/skillsets to perform the
tasks defined in this Manual as they relate to their assigned facility, contract, supplies or services.
b. Review requests for technical assistance and provide necessary support.
c. Determine the need for inspection stamps for FS under their purview in accordance with
(IAW) section 4. of this Manual and the Guidebook on the Resource Page of this Manual .
d. Complete applicable First Level Supervisor Reviews (FLSR) for tasks defined in this
Manual IAW the prescribed time constraints detailed in prevailing guidance.
e. Complete the Product Acceptance Authorization Form, as required, in paragraph 6.2 of
this Manual.
DCMA-MAN 2101-01, March 24, 2019
SECTION 2: RESPONSIBILITIES 8
f. Relay any negative performance and acceptance information to the Administrative
Contracting Officer (ACO) for potential consideration actions and to the industrial specialist for
potential impacts to delivery or integrated master product schedules.
2.7. ADMINISTRATIVE CONTRACTING OFFICER. The Administrative Contracting
Officer (ACO) will:
a. Review and, if warranted, act upon consideration recommendations that are provided by
the FS. See section 6.3 of this Manual.
b. Assist with decisions regarding the acceptability of the supplies, the processes, and the
requirements, as well as action to correct defects.
c. Consider specific written instructions from the PCO.
2.8. FUNCTIONAL SPECIALIST. The FS will:
a. Execute and adjust surveillance based on risk assessment (e.g., analysis of data collected,
facility awareness, etc.).
b. Ensure that surveillance events are documented and accomplished IAW the surveillance
plan.
c. Issue Corrective Action Request(s) (CAR) IAW DCMA-MAN 2303-04, “Surveillance -
Document and Provide Feedback” when contractual nonconformances are independently
identified during surveillance or when verified nonconformances are identified by customer.
d. Communicate with Functional Lead/Supervisors when problems/concerns arise during the
execution of the surveillance plan.
e. Determine the need for FS support (e.g., QA Engineer (QAE) assistance or other FS
assistance) to perform the necessary surveillance. The requestor will send the request in writing
to their FLS.
f. Participate in the Postaward Orientation Conference (PAOC) and/or conduct a Functional
Specialist Meeting (FSM) when conditions as specified in paragraph 3.3. Exist.
g. As required, document and execute a First Article Test (FAT), Production Lot Test (PLT)
and/or Production Verification Testing (PVT) surveillance strategy.
h. Notify the Place(s) of Performance (POP) FS that FAT and/or PLT requirements are part
of the contract.
i. Conduct meetings with the contractors as needed to ensure all parties understand the
requirements (i.e., FAT and/or PLT, place and mode of acceptance, make or buy decisions, etc.),
as required.
DCMA-MAN 2101-01, March 24, 2019
SECTION 2: RESPONSIBILITIES 9
j. Prepare and submit recommendation for considerations to the ACO in regards to FAT,
PLT and PVT IAW section 3 and section 6.3 of this Manual.
k. Relay any negative performance e.g. CARs, PQDRs, delay in deliveries etc. and
acceptance data e.g. rejections, information to the Administrative Contracting Officer (ACO) and
the Industrial Specialist (IS).
2.9. CONTRACT MANAGEMENT OFFICE INSPECTION STAMP CUSTODIAN. Until
the complete elimination of the use of fiscal stamps Stamp Custodians must be maintained. The
CMO Inspection Stamp Custodian will:
a. Ensure inspection stamps are inventoried and are serviceable.
b. Notify the OUD when there is a change in custodian.
c. Maintain inspection stamp records.
d. Issue inspection stamps as required.
e. Notify the Functional FLS and Functional Director of lost or stolen inspection stamps.
f. Update the Master Inventory and Custodian Lists the link is on the Resource Page of this
Manual.
2.10. INSPECTION STAMP CUSTODIAN OPERATIONAL UNIT DIRECTORATE.
Until the complete elimination of the use of fiscal stamps Stamp Custodians must be maintained.
The OUD Inspection Stamp Custodian will:
a. Ensure inventories are completed and accurate, and the Inspection Stamp List is updated
accordingly on the DCMA 360 the link is on located the Resource Page of this Manual.
b. Maintain inspection stamp on-hand quantities to distribute to CMOs as required.
c. Ensure the Custodian information is correct on the Custodian List on the DCMA 360 the
link is located on Resource Page of this Manual.
d. Review and approve/disapprove requests from CMOs for inspection stamps IAW section
4.of this Manual and the Guidebook on the Resource Page of this Manual.
DCMA-MAN 2101-01, March 24, 2019
SECTION 3: FIRST ARTICLE AND PRODUCTION LOT TESTING 10
SECTION 3: FIRST ARTICLE, PRODUCTION LOT TESTING AND
PRODUCTION VERIFICATION TESTING
3.1. CONTRACT RECEIPT AND REVIEW. FAT, PLT and/or PVT requirements may
appear in contracts in one of the following methods, which may affect the FS’s surveillance
strategy:
a. Contractor Testing. IAW FAR 52.209-3, “First Article Approval - Contractor Testing,
the contractor is required to perform the actual testing and submit a test report to the PCO or the
ACO for approval.
b. Government Testing. IAW FAR 52.209-4, “First Article Approval - Government
Testing,” the Government is required to perform the actual testing to verify the supplies conform
to specifications.
c. PVT is performed by the government test labs. When PVT is required DLA will issue a
Quality Letter of Instruction to invoke it. The CMO will notify the contractor that PVT is
invoked and testing will be performed.
3.2. FUNCTIONAL SPECIALIST ASSISTANCE FOR SOFTWARE. When the FAT, PLT
and/or PVT requirement includes testing of software embedded in the end item, system, or stand-
alone software item, the FLS must ensure a DCMA certified software professional is contacted
for functional assistance.
3.3. PARTICIPATE IN POSTAWARD ORIENTATION CONFERENCE OR HOLD A
FUNCTIONAL SPECIALIST MEETING.
a. The FS will conduct a FSM when a PAOC is not held if any of the following conditions
apply for either Contractor or Government FAT, PLT and/or PVT requirements:
(1) The contractor is performing a FAT, PLT and/or PVT for the first time.
(2) FAT, PLT and/or PVT requirement is for a Critical Safety Item.
(3) When an extended time has passed as defined by the PCO since the last FAT and/or
PLT was performed by the contractor.
b. Notify the PCO for guidance when the contractor has significant personnel changes,
tooling, machinery, facility, etc. since the last FAT, PLT and/or PVT that may affect
manufacturing and/or testing processes.
c. At a minimum, the FS must review and discuss the following criteria at a FSM:
(1) Specific first article/production lot/production verification contractual requirements.
DCMA-MAN 2101-01, March 24, 2019
SECTION 3: FIRST ARTICLE AND PRODUCTION LOT TESTING 11
(2) Any inspections or tests to be performed by the contractor and/or DCMA at
subcontractor locations.
(3) Government inspection hold points.
(4) Required plans or reports.
d. Contractors who have repetitive contracts or orders with FAT, PLT and/or PVT
requirements or a contractor performing satisfactorily on identical items may not require FSM.
3.4. DEVELOP FIRST ARTICLE TEST, PRODUCTION LOT TEST AND/OR
PRODUCTION VERIFICATION TEST SURVEILLANCE PLAN OR UPDATE THE
CURRENT CONTRACTOR FACILITY OR PROGRAM SURVEILLANCE PLAN.
a. Contractor or Government Testing. The surveillance plan must include:
(1) Validation of the contractor’s inspection/test records and test reports that clearly
demonstrate the supplies are in conformance to the contract and technical data package.
(2) Inspections for any characteristics identified by contractual documents, Quality
Assurance Letter of Instruction, and Letter of Delegation are accomplished and documented.
(3) Validation that required records and/or reports are sent to the approval authority.
(4) When required, validate the manufacturing processes, materials, and facilities used to
produce the FAT and/or PLT production quantity are at the same facilities IAW FAR 52.209-3,
Alternate I paragraph (i) and FAR 52.209-4, Alternate I, paragraph (j), respectively.
b. Specific to Contractor Testing. The surveillance plan must ensure:
(1) Validation of the contractor’s inspection of characteristics or processes identified in
the FAT and/or PLT report by independently inspecting, witnessing or verifying as identified in
the contract and technical data package. The plan also must include processes that are deemed a
risk at subcontractor facilities.
(2) If sampling is authorized in the contract, perform Process Evaluations (PE) and/or
Deliverable Product Evaluations (DPE) of all characteristics to the degree necessary to establish
confidence of conformance to the contract and technical data package.
c. Specific to Government Testing. The surveillance plan must ensure:
(1) Any additionally required documentation (e.g., material certifications, process
operations sheets, inspection method sheets, copies of drawings, and any other pertinent
documentation) is included with the exhibit(s) designated for testing as stated in the contract.
(2) Validation that the packaging exterior is clearly marked (as applicable).
DCMA-MAN 2101-01, March 24, 2019
SECTION 3: FIRST ARTICLE AND PRODUCTION LOT TESTING 12
d. The FAT, PLT and/or PVT can be part of the existing facility or program plan or a stand-
alone plan.
3.5. GOVERNMENT SURVEILLANCE HOLD POINTS.
a. During FAT, PLT, PVT surveillance planning, the FS must determine if there is a
customer mandated requirement and/or an identified risk for surveillance hold points at
applicable manufacturing process steps.
b. The FS must notify the contractor in writing of hold points. The contactor must
acknowledge receipt and a signed copy will be maintained with the surveillance records. The
notification should state if the contractor’s planning steps are changed or deleted, the contractor
must notify the FS.
3.6. DETERMINE THE NEED FOR SURVEILLANCE AT GOVERNMENT
SUBCONTRACTOR LEVEL. If risk assessment warrants, and surveillance for critical or
major characteristics/processes can only be performed at a subcontractor’s facility, a request for
subcontract surveillance from the prime FS must be executed IAW DCMA MAN 2101-04,
Delegate Surveillance,” to the cognizant CMO performing surveillance activities at the
subcontractor.
3.7. EXECUTE FIRST ARTICLE TEST, PRODUCTION LOT TEST AND/OR
PRODUCTION VERIFICATION TEST SURVEILLANCE PLAN.
a. The FS performs surveillance as identified on the surveillance plan.
b. The FS ensures the contract specified number of PLT/PVT samples are randomly selected
for test/evaluation (as applicable). Refer to random number generator tool located on the
Resource Page of this Manual.
c. The FS must identify and document the product characteristics and/or processes inspected,
verified, witnessed or tested to the FAT and/or PLT approval authority.
3.8. NOTIFY ADMINISTRATIVE CONTRACTING OFFICER AND PROCURING
CONTRACTING OFFICER OF ANY NONCONFORMANCE(S), OR REQUEST(S) FOR
VARIANCE AND REQUEST INSTRUCTIONS.
a. The FS will notify the ACO who will contact the PCO of the following circumstances:
(1) Any identified nonconformance of the FAT, PLT and/or PVT unit.
(2) Any request for variance by the contractor (with the appropriate FS recommendation
for the variance) and request instructions from the PCO as to how to proceed with the FAT.PLT
and/or PVT requirement.
DCMA-MAN 2101-01, March 24, 2019
SECTION 3: FIRST ARTICLE AND PRODUCTION LOT TESTING 13
b. The FS will ensure variance requests are processed IAW DCMA-MAN 2301-06,
Discrepancy Processing,and approved by the ACO and/or PCO prior to shipment of
production units.
c. The FS will also recommend to seek consideration to the ACO for repeat testing. Include
proposed remedies. Considerations are a contract modification that the contracting officer
performs this function. See DCMA-MAN 2301-06 and FAR 46.407 “Nonconforming Supplies
or Services” for additional information. The recommendation will consist of as applicable:
Labor cost
Defects noted
Trend analysis
Note is the item safe to use and will perform as intended
Note is it a one off or a systemic issue and will it affect other systems or end items
Total dollar amount for consideration
Repeat discrepancies
Corrective Actions issued
d. The FS will notify the IS and any other appropriate stakeholders of any impact or delay in
production. For SCD A & B contracts the CMO Commander will be notified along with the
ACO. The ACO will document all consideration efforts and whether it was pursued or not.
3.9. DOCUMENT FIRST ARTICLE TEST AND/OR PRODUCTION LOT TEST
RESULTS. The FS may use a DD Form 1222, “Request for and Results of Test,” or equivalent
to include with the contractor’s FAT and/or PLT report and/or to report the results of the
inspection of the first article/production lot units. When required the DD Form 1222 or
equivalent should be separate from and in addition to any contractor reports. When the DD
Form 1222 is required the FS must include the following minimum information:
a. A list of names, activities, and telephone numbers of individuals providing technical
assistance to the FS and other Government personnel participating in the FAT and/or PLT.
b. A statement identifying the characteristics specifically inspected, witnessed, or verified by
the FS. Alternatively, the FS may attach copies of the results if they clearly identify the
characteristics actually inspected, witnessed or verified, by the FS using “Observation Record,”
located on the Resource Page of this Manual or equivalent DPE Record is acceptable.
c. A detailed description of any nonconformance in the FAT and/or PLT units, test results or
departures from the contractually specified FAT and/or PLT procedures (if applicable).
d. A statement identifying the ACO or PCO by name, title, activity, and telephone number
authorizing the shipment of nonconforming FAT and/or PLT units or test reports (if applicable).
e. A recommendation for approval or disapproval when the contract requires contractor
conducted FAT and/or PLT.
DCMA-MAN 2101-01, March 24, 2019
SECTION 3: FIRST ARTICLE AND PRODUCTION LOT TESTING 14
3.10. FIRST ARTICLE TEST AND/OR PRODUCTION LOT TEST APPROVAL.
a. When the PCO retains FAT and/or PLT approval, conditional approval, or disapproval
authority, the formal notification of the decision to the contractor must be signed by the PCO.
(1) When FAT and/or PLT approval, conditional approval, or disapproval is received
from other than the PCO (i.e., the technical activity), the FS must forward a copy to the
appropriate ACO for their coordination with the PCO. Formal notice to the contractor must be
signed by the PCO.
(2) When the PCO delegates FAT and/or PLT approval, conditional approval, or
disapproval authority to the ACO, formal notification to the contractor must be signed by the
ACO.
b. The approval of a nonconforming FAT and/or PLT unit must not be construed as
authorization to accept production items containing any nonconformance with the contractual
requirements. For retests submit request for considerations to the ACO as outlined in section
6.3. Notify the IS with any potential production/delivery delays and the estimated time for
recovery.
c. Contracts may require FAT and/or PLT units to be manufactured using the same facilities,
manufacturing processes, methods, and materials as the production units. When this or similar
requirements are included in the contract, and the FS observes any changes that may affect the
quality of supplies, the FS must advise the Contracting Officer of the circumstances. FS must
issue a CAR, if warranted, and withhold formal acceptance pending further direction from the
Contracting Officer.
d. Before accepting and/or authorizing shipment of any production quantities, FS must
verify and document that the contractor’s corrective action(s) resulting from the FAT and/or PLT
were implemented and any deficiencies noted in letters of conditional approval were corrected.
3.11. FIRST ARTICLE TEST AND/OR PRODUCTION LOT TEST UNIT SHIPMENT.
a. Prior to shipment of a FAT unit or test report, the Contract Administrative Office (CAO)
must provide the receiving activity with advance notification of the shipment IAW FAR 9.307,
“Government Administration Procedures.”
b. The FS must not authorize the contractor to ship FAT and/or PLT units or test reports
containing a known or suspected nonconformance, unless specifically directed in writing to do so
by the Contracting Officer.
3.12. RECORDS MANAGEMENT. FAT, PLT and/or PVT surveillance actions are
maintained with surveillance records. Records may include but are not limited to:
a. DD Form 1222.
DCMA-MAN 2101-01, March 24, 2019
SECTION 3: FIRST ARTICLE AND PRODUCTION LOT TESTING 15
b. FSM record and any other supporting documents related to FAT, PLT and/or PVT
surveillance.
c. FAT, PLT and/or PVT Approval, Disapproval or Conditional Approval Letter.
1
DCMA-MAN 2101-01, March 24, 2019
SECTION 4: INSPECTION STAMPING 16
SECTION 4: INSPECTION STAMPING
4.1. INSPECTION STAMPS. It is DCMA’s policy to eliminate Inspection Stamps.
Completed surveillance tasks will be documented in the DCMA surveillance report. Currently,
Inspection Stamps should only be used for NASA and NSEO as required by current MOAs.
Guidance will be found on the Resource Page of this Manual when the use of Inspection Stamps
are required.
DCMA-MAN 2101-01, March 24, 2019
Section 5: Standard Inspection Requirements 17
SECTION 5: STANDARD INSPECTION REQUIREMENTS
5.1. DETERMINING THE ACCEPTABILITY OF THE CONTRACTORS INSPECTION
SYSTEM. FAR 52.246-2, “Inspection of Supplies - Fixed-Price”, FAR 52-246-3, “Inspection
of Supplies - Cost-Reimbursement”, FAR 52-246-4, “Inspection of Services - Fixed-Price”, FAR
52-246-5, “Inspection of Services - Cost-Reimbursement”, FAR 52-246-6, “Inspection - Time-
and-Material and Labor-Hour”, FAR 52-246-7, “Inspection of Research and Development -
Fixed-Price” and FAR 52-246-8, “Inspection of Research and Development - Cost-
Reimbursementrequires contractors to have an inspection system acceptable to the
Government.
a. Regardless of whether there is a higher level quality requirement (i.e., AS9100, ISO 9000,
etc.), the Standard Inspection System Checklist or equivalent is required to be executed for
Government contracts to determine the acceptability of the contractor’s inspection system.
b. Where commercial contracts require government quality oversight, requirements may be
outlined within the contract or addendums. When more detail is needed, contact the PCO for
direction. These documents may limit Government oversight to Kind, Count and Condition or
may include detailed inspection requirements.
5.2. ASSESS THE CONTRACTOR’S INSPECTION SYSTEM.
a. Prior to accepting supplies and services (for services when applicable), the FS must
determine whether the contractor has and maintains an inspection system that is acceptable to the
Government. The FS will perform an initial evaluation and at a minimum, this evaluation will be
on an annual basis thereafter. Prime contractors are responsible for assuring that all supplies and
services procured from their subcontractors conform to all contract requirements. The adequacy
of the contractor’s inspection system is determined based on supplier quality history, complexity,
criticality, and contractor’s controls of their manufacturing and assembly operations.
b. The FS must determine the acceptability of the contractor’s inspection system based on the
effective quality controls of critical processes and critical and major technical characteristics of
design.
c. FS that have a question or concern regarding safety of the facility, should follow the
procedure in DCMA-MAN 4201-16, "Safety and Occupational Health Program" and the safety
Resource Page.
d. The FS should consult with DCMA Contract Safety Manager/Specialist (CSM/CSS) for
contract safety specific requirements, or when there is concern about safe processes. Refer to
DCMA-MAN 2301-07, "Contract Safety."
e. Surveillance activities must verify that contractor records:
DCMA-MAN 2101-01, March 24, 2019
Section 5: Standard Inspection Requirements 18
(1) Are available to the Government during contract performance and for as long as the
contract requires.
(2) Provide evidence of all inspections made IAW the inspection system and the
outcomes.
(3) Are complete to demonstrate conformity to technical requirements, which should
include, as applicable:
(a) Nature (characteristics) and number of observations made (e.g., documented
results match the method of measurement if the requirement is a dimension .100 +.002 (Variable)
the measured dimension .101 is recorded good or bad (attribute)).
(b) Type and number of deficiencies found.
(c) Number of approved and rejected product and/or services.
(d) Who performed the inspection?
(e) Date of inspection.
(f) Traceability to the supplies (e.g., nomenclature, part number, National Stock
Number, serial number, if available).
(g) Traceability to material properties may include Mill Certifications, Heat Lot
Numbers, Forge Lot Numbers, and Chemical/Physical Analysis Reports.
f. Surveillance activities must verify the contractor:
(1) Has adequate quantity and type of measuring and test equipment for examination of
the items procured.
(2) Maintains an acceptable inspection system IAW paragraph 5.2.b of this Manual to
verify the accuracy, precision, and repeatability of measurements taken with measuring and test
equipment which includes records, traceability to a recognized national standard, and a recall
system.
(3) Maintains records of all inspections and tests and their outcomes.
(4) Understands and properly applies statistically valid sampling plans when used.
(5) Implements corrective action and has a process for control of nonconforming
material activities. The contractor:
(a) Has a system for identifying and segregating nonconforming material.
DCMA-MAN 2101-01, March 24, 2019
Section 5: Standard Inspection Requirements 19
(b) Understands the requirements for presenting nonconforming material to the
Government for acceptance.
(c) Maintains records for corrective action.
g. When the contractor provides either a material or process Certificate of Conformance
(CoC) (not to be confused with FAR clause 52.246-15) and/or a Certified Test Report from a
subcontractor, the FS must have a basis for confidence in the validity of the CoC or Certified Test
Report presented. The FS may, on a random basis, request the contractor provide evidence of
traceability for materials.
5.3. DOCUMENT THE RESULTS OF INSPECTION SYSTEM REVIEW. The FS must
document the results of inspection systems acceptability in the DCMA surveillance report. The
Standard Inspection System Checklist contains suggested guidance for evaluating the
acceptability of the contractor’s inspection system. See the Standard Inspection Checklist located
on the Resource Page of this Manual. When contractual nonconformances of the inspection
system or with supplies or services which may delay delivery or Progress Payments notify the IS
and ACO so that production delay necessary to complete corrective actions may be considered for
input.
5.4. ISSUE CORRECTIVE ACTION REQUEST. The FS must initiate an appropriate level
CAR when a nonconformity with contractual inspection system characteristics is discovered.
The FS will monitor surveillance results during production to ensure that corrective actions are
implemented and still are effective. Notify the ACO of the nonconformance(s) and corrective
actions plan for their review and action as appropriate. Some nonconformances may have to be
elevated to the PCO.
5.5. CONTRACTOR IDENTIFIED DEFICIENCY: When a contractor self identifies
nonconformances that effect delivery schedule, notify the appropriate FS. See DCMA-MAN
2303-04 “Surveillance – Document Results, Corrective Action & 10 Provide Feedback”.
DCMA-MAN 2101-01, March 24, 2019
Section 6: Product Acceptance and Release 20
SECTION 6: PRODUCT ACCEPTANCE AND RELEASE
6.1. AUTHORIZED PERSONNEL PERFORMING ACCEPTANCE. When Acceptance is
identified within the contract for DCMA to perform inspection and/or acceptance, the ACO,
Contracting Officer’s Representative (COR), FS, or other Government official performing
Acceptance must make a determination that supplies or services meet contractual requirements.
a. The FS (e.g., QA and Software Professional Development Program (SPDP) certified
personnel) possesses the prerequisite training and skillset(s) to adequately determine conformity
of supplies or services to contract requirements, and perform the acceptance functions within
DCMA when authorized IAW paragraph 6.2 of this Manual. ACOs who choose to perform
acceptance should seek input from the FS or CORs concerning whether the supplies or services
meet contract requirements. ACOs must document, with supporting rationale, to the contract file
any determination to waive FS or COR quality assurance input prior to acceptance.
b. To accept supplies or services on behalf of the U.S. Government, Acceptance will be
based upon traceable objective evidence that Government Contract Surveillance (GCS)
was performed IAW planned surveillance by a certified or qualified FS in the appropriate
skill set(s) or QA personnel will:
(1) Be certified in or working towards a Defense Acquisition Workforce Improvement
Act (DAWIA) Level l certification in a DOD career field aligned to the position.
(2) Be assessed and certified in QA system skill set core, and applicable core plus
courses.
(3) Be certified in the applicable technical skill sets for the supplies or services the FS is
accepting. When GCS is performed by Host Nations, the acceptance will be based on the
International Agreement with that nation. (Standardization Agreement 4107, as applicable, or the
applicable country's Memorandum of Understanding).
c. In the event the above conditions cannot be met due to resource constraints or training
availability, the following interim Limited solution may be utilized to continue mission support.
On an exception basis, DCMA Commanders or Functional Directors may:
(1) Authorize a FS to accept supplies and/or services once the FLS has successfully
completed an “initialFLSR on “Product Acceptance and Release” prior to recommending a
Limited Authorization. This initial” FLSR will be documented on the DCMAF 2101-01 by
checking the FLS Assessment block and the Functional Director or Commander signature in the
appropriate block.
(2) Limited authorizations must not exceed 12-months in duration and reissuance of
Limited authorizations are not permitted.
d. With respect to software products, only DCMA personnel who are SPDP certified may
accept software.
DCMA-MAN 2101-01, March 24, 2019
Section 6: Product Acceptance and Release 21
6.2. ACCEPTOR AUTHORIZATION. After this review is completed, the DCMAF 2101-01
“Product Acceptance Authorization Form” (template) located on the Resource Page of this
Manual must be completed and filed IAW guidance under the Guidance section of the Resource
Page of this Manual. The FLS must grant the FS access to the system of record before
acceptance can be accomplished.
a. The authorization to perform acceptance is based on the FLS’s knowledge, observation
and review of training and skills of the FS.
b. To maintain acceptance authorization, the FLS must perform an FLSR IAW FLSR
guidance to ensure relevant skills are current and maintained at which time the authorization
form must be renewed and refiled.
c. Acceptor Revocation: Should an FLS find that the FS is lacking training or skills
necessary to perform the acceptance function, the FLS will withdraw authorization to perform
Acceptance and revoke access to system of record to prevent further Acceptance unless
immediate corrective action to the deficiency can be accomplished.
6.3. PRIOR TO ACCEPTANCE. The FS will ensure that all nonconforming material and/or
Variances are dispositioned and have been adjudicated prior to Acceptance IAW DCMA-MAN
2301-06, “Discrepancy Processing” and see FAR 46.407 for additional information. The
adjudication will ensure all requests for considerations have been coordinated with the ACO and
documented. The FS in coordination with the ACO will determine when to seek consideration
based on established criteria. The FS will submit all pertain documentation to the ACO with
recommendation needed to determine considerations. Include proposed remedies.
Considerations are a contract modification that the contracting officer performs this function.
See DCMA-MAN 2301-06 and FAR 46.407 “Nonconforming Supplies or Services” for
additional information. The recommendation will consist of as applicable:
Labor cost
Defects noted
Trend analysis
Note is the item safe to use and will perform as intended
Note is it a one off or a systemic issue and will it affect other systems or end items
Total dollar amount for consideration
Repeat discrepancies
Corrective Actions issued
6.4. GOVERNMENT CONTRACT SURVEILLANCE.
a. Prior to acceptance, the FS must ensure planned surveillance was performed IAW the
surveillance plan, all contractor tests and inspections are completed, and supplies or services
meet the contractual requirements. If supplies or services do not meet the contract requirements,
the FS must not accept, or recommend acceptance, of the supplies or services. When a
nonconformance is found by a Government Representative, a CAR will be issued by the FS.
DCMA-MAN 2101-01, March 24, 2019
Section 6: Product Acceptance and Release 22
b. When the supplies under consideration are software products, the FS must determine
whether:
(1) The supplies are a stand-alone contract line item.
(2) The supplies are embedded in an end item or system.
c. If the software is embedded in the end item or system, prior to acceptance of the end item
or system, inspection and acceptance of the software element of the system must be coordinated
with SPDP certified personnel. Document acknowledgment that the embedded software meets
contractual requirements.
6.5. AUTHORIZE SHIPMENT OF SUPPLIES. FAR 46.505(a) provides that formal
acceptance transfers title of supplies to the Government, “regardless of when or where the
Government takes physical possession, unless the contract specifically provides for earlier
passage of title.” The CAO must, consistent with the contract terms and conditions, determine
the appropriate method of authorizing shipment release.
a. Where appropriate, qualified FS (i.e., QAS, QAE, SPDP certified) are authorized to
release supplies using Alternative Release Procedures (ARP) IAW DFARS 246.471,
“Authorizing Shipment of Supplies.” Authorized personnel may also accept supplies and
services using CoC IAW DFARS 246.504, “Certificate of Conformance, and FAR 52.246-15,
“Certificate of Conformance.” ARP and CoC are applied as described in this Manual.
b. ARP and CoC will not be authorized on any contracts involving shipments for NASA,
Level 1/Subsafe, the Navy Special Emphasis Program, unless specifically authorized in writing
by the PCO. ARP is not authorized for Foreign Military Sales (FMS) shipments.
c. The primary difference in the requirements for ARP and CoC is the execution of GCS.
(1) ARP requires continuing surveillance IAW the GCS Plan (e.g., PE or DPE)
depending on the risks identified. ARP allows QA personnel to focus on areas of risk and does
not require the contractor to wait for QA personnel to sign or accept the RR/RRR or DD Form
250 prior to shipping the supplies. Examples are if packaging, final inspection or the RR/RRR
input is low risk, the use of ARP may be appropriate. The use of ARP is to eliminate the delay
between the time the contractor is ready to ship and the time when DCMA performs Acceptance.
(2) CoC is used in lieu of GCS. FAR Clause 52.246-15 must be included in the contract
and invoked in writing by the CAO.
(3) In each case, the contractor releases the supplies when they are ready for shipment
IAW the contract, and the RR/RRR or DD Form 250 are completed IAW DFARS, Appendix F.
d. When the conditions described in DFARS 246.471(b) are met, and ARP is used, the
following applies:
DCMA-MAN 2101-01, March 24, 2019
Section 6: Product Acceptance and Release 23
(1) ARP does not relieve contractors from complying with U.S. Government source
inspection requirements and must not be used in lieu of Government Contract surveillance
activities.
(2) No contract clause is required to utilize ARP.
(3) ARP must be authorized in writing by the CAO.
(4) ARP is applicable for supplies but not services.
(5) ARP is available/applicable to both prime contractors and sub-tier contractors.
e. ARP may be authorized at the facility, program, product line, or contract level. When the
ARP methodology is applied, ensure that the RR/RRR or DD Form 250 is completed IAW
DFARS, Appendix F requirements.
f. When shipments are made via ARP, the contractor is only required to select the
appropriate “radio button” on the RR/RRR screen in lieu of annotating the statement identified in
DFARS 246.471.
g. When authorized IAW FAR clause 52.246-15, the CAO may accept supplies via a CoC.
IAW DFARS 246.504, before authorizing a CoC for aviation or ship critical safety items, obtain
the concurrence of the head of the design control activity in writing. When used, CoC must be
authorized or withdrawn in writing on a contract-by-contract basis. Acceptance via CoC is
preferred, unless there is insufficient data to assess contractor performance history, the customer
has imposed mandatory surveillance tasks, or there is documented evidence of significant
adverse contractor performance. When FAR 52.246-15 clause is included in contracts, the PCO
has assured that:
(1) Acceptance on the basis of a contractor’s CoC is in the Government’s interest.
(2) Small losses would be incurred in the event of a defect.
(3) The contractor’s reputation or past performance, it is likely that the supplies or
services furnished will be acceptable and any defective work would be replaced, corrected, or
repaired without contest.
h. When determining the use of CoC, the following apply:
(1) CoC clause must be contained in the contract.
(2) CoC must be authorized in writing by the CAO.
(3) CoC is applicable to supplies and services.
DCMA-MAN 2101-01, March 24, 2019
Section 6: Product Acceptance and Release 24
(4) CoC is available/applicable to prime contractor; invoking the CoC on the prime
contract results in no Government surveillance at sub-tier contractor’s supporting the prime
contract.
(5) If a delegation is warranted to mitigate risks identified at a subcontract level, CoC is
not appropriate to be authorized.
i. It is appropriate for CAO to invoke CoC when conditions warrant its use. When the CoC
methodology is applied, ensure that the DD Form 250 is completed IAW DFARS, Appendix F
requirements.
j. When shipments are made via CoC the contractor is only required to select the appropriate
“radio button” on the RR/RRR screen in lieu of annotating the signed certificate identified in
FAR 52.246-15.
6.6. PRODUCT ACCEPTANCE DOCUMENT SAMPLING. Document sampling is
required when a risk is identified within the contractor’s process.
a. Performing risk-based Process Evaluations of the contractor's process is the preferred
method for ensuring the RRs/RRRs meet their contractual requirements.
b. If using the DPE method for surveillance and multiple RRs/RRRs are presented at one
time, sampling may be used to verify that the RRs/RRRs are correct.
c. Sampling, if used, must be accomplished using a zero-based Acceptable Quality Level
commensurate with the risk associated with the contractor’s RR/RRR development process.
d. The FS must prepare DPE records showing which RR/RRR were reviewed as described in
paragraph 6.5.c of this Manual, (i.e., if there are twenty RRs/RRRs presented for acceptance and
five are reviewed, record the shipment number of those five on the DPE record).
e. The same must apply when processing a DD Form 250 IAW DFARS, Appendix F.
6.7. VERIFYING PRODUCT ACCEPTANCE DOCUMENTS. Per DFARS 252.232-7003,
“Electronic Submission of Payment Requests and Receiving Reports” the preferred method is an
electronic form of the RR/RRR for (contractor) submission of payment requests. However, there
may be circumstances when a contractor submits a DD Form 250.
a. Personnel accepting supplies and services via RR/RRR or DD Form 250 will use
rejections in their data analysis as the basis to determine the risk referenced in paragraph 6.4.
Data must be analyzed to identify process drivers, identify problems and solutions, and track
progress in terms of rejection rates.
b. Final Shipments: Final acceptance documents, verify the contractor:
(1) Has placed a Z” at the end of the shipment number for final shipment.
DCMA-MAN 2101-01, March 24, 2019
Section 6: Product Acceptance and Release 25
(2) Has placed a “Z” in the Advice Code (RR/RRR) or below the quantity (DD Form
250 block 17) when the final shipments contains an authorized variation of quantity and an
underrun condition exists IAW DFARS Appendix F paragraphs F301 or F401.
c. Critical fields: When validating RR/RRR, as a minimum ensure the following fields
match the contract and/or delivery order prior to signing:
(1) Contract Number/Order number (Procurement Instrument Identifier/Procurement
Instrument Identifier Number/Supplemental Procurement Instrument Identification Number).
(2) Shipment Number.
(3) Item Description closely matches the contract Item Description, the product
identification, Part Number or National Stock Number match.
(4) Contract Line Item/CLIN / Sub Line Items/SLIN / Exhibit Line Items/ELIN.
(5) Unit of Measure (i.e., Lot or Each).
(6) Ship To/Mark for Department of Defense Activity Address Code/DoDAAC.
(7) Military Standard Requisition Issue Procedures/MILSTRIP if applicable.
(8) Quantity (within the specified variance of the contract or less than or equal to the
contract quantity).
(9) The appropriate radio button is checked (i.e., ARP, CoC, and/or FMS).
(10) FMS shipments:
(a) FMS Case Identifier (mandatory).
(b) FMS Military Standard Requisitioning and Issue Procedures/MILSTRIP
(mandatory).
(c) Ship To/Mark for Location Code/ Military Assistance Program Address
Code/MAPAC (mandatory).
(d) Unit Price (mandatory).
(e) Cube (optional).
(f) Project Code (optional).
(g) Transportation Account Code (optional).
DCMA-MAN 2101-01, March 24, 2019
Section 6: Product Acceptance and Release 26
(h) Special Package Markings/Special Handling Requirements (optional).
(i) Military Articles and Services List/MASL (optional).
(j) Transportation Control Number/TCN (optional).
d. Ensure the contractor maintains the system of record (e.g., Procurement Integrated
Enterprise Environment (PIEE)), WAWF application data integrity by verifying Aging RR/RRR
over 30 days are processed or rejected back to the contractor or the contractor confirms, deletes
or voids the ones no longer valid. Target population are those in “Correction Required,” “In
Process,” “Submitted,” “Resubmitted,” and “Draft” status along with Active and Archive.
(1) Contact the POP cognizant DCMA office (when applicable) for resolution of Aging
RR/RRR.
(2) Where contractors no longer exist or do not have contracts with the Government,
contact the next higher OUD for resolution.
6.8. PROCESS CORRECTED ACCEPTANCE DOCUMENTS. When corrections are
needed for an acceptance document, corrected RR/RRR must be processed using the system of
record and corrected DD Form 250s must be processed IAW the correction instructions
contained in DFARS, Appendix F.
6.9. PROCESS A REPLACEMENT ACCEPTANCE DOCUMENT. When replacing a lost
or missing RR/RRR, go to the system of record and reprint the document. For a lost or missing
DD Form 250 acceptance document, the date of acceptance on the replacement copy will be the
actual date of acceptance from the original acceptance document.
6.10. FINANCIAL IMPROVEMENT AUDIT REMEDIATION GUIDANCE. Financial
Improvement Audit Remediation documentation requirements are on the Resource Page of this
Manual under the Guidance section and will be followed.
DCMA-MAN 2101-01, March 24, 2019
GLOSSARY - DEFINITIONS 27
GLOSSARY
G.1. DEFINITIONS. These terms and their definitions are for the purpose of this policy
issuance.
Acceptance. The act of an authorized representative of the Government by which the
Government, for itself or as agent of another, assumes ownership of existing identified supplies
tendered or approves specific services rendered as partial or complete performance of the
contract.
Capability Manager. The capability manager is responsible to serve as Agency proponent for a
capability and conduit to the council, participate as a voting member of the DCMA
Requirements Oversight Council, champion strategic planning initiatives to include, but not
limited to, development and refinement of DCMA goals and initiatives, exercise decision making
authority and lead the decision making process and facilitate consensus whenever possible.
Employ conflict resolution internal and external to the board, prioritize, assign and manage
activities and tasks. Establish working groups, integrated process teams, tiger teams, and Lean
Six Sigma/Business Process Re-engineering project teams as required.
Contract quality requirements. The technical requirements in the contract relating to the
quality of the supplies or services and those contract clauses prescribing inspection, and other
quality controls incumbent on the contractor, to assure that the supply or service conforms to the
contractual requirements.
Contractor. An organization or a separate entity of it, such as an affiliate, division, or plant that
that produces supplies or services under contract for the Government.
Deliverable Product Evaluation (DPE) or Service Evaluation. Deliverable Product or Service
Evaluation is a surveillance category that is used to evaluate deliverable product or services.
Deliverable product evaluation is used for evaluating what will eventually be provided to the
Government for acceptance. These evaluations can be performed in any phase of the product’s
completion and include those on hardware, software, or CDRLs. Deliverable service evaluation
is used for monitoring compliance of deliverable services throughout a specified period of time
based on Government requirements, and may involve periodic acceptance and performance
assessments for progress and compliance. This Deliverable Product or Service Evaluation can be
used for assessing contractual deliverables in DCMA administered contracts, contracts awarded
by DCMA, and contracts with delegations (e.g., NASA) to DCMA.
Functional Specialist. Functional Specialists are personnel assigned to perform various tasks or
functions in support of the Agency’s mission (e.g., Administrative Contracting Officer, contract
administrator, Contracting Officer Representative, cost monitor, engineer, industrial specialist,
IT specialist, or quality assurance specialist).
Government Contract Surveillance. Surveillance is a function of contract administration used
to determine or assess contract progress and/or compliance through “data collection and
analysis.” In DCMA, surveillance is often a multifunctional insight effort to review and analyze
DCMA-MAN 2101-01, March 24, 2019
GLOSSARY - DEFINITIONS 28
contractor plans, schedules, policies/procedures, systems, processes, process outputs, product, or
services. Surveillance includes reviews for adequacy (when applicable) and to determine
compliance to contractual, statutory, regulatory, or contractor requirements. Surveillance
involves collecting data and assessing it to make a determination or conclusion.
Inspection. Examining and testing supplies or services (including, when appropriate, raw
materials, components, and intermediate assemblies) to determine whether they conform to
contract requirements.
Nonconformance. The non-fulfillment of a requirement. This includes a failure of a
characteristic to conform to the requirements specified in the contract, drawings, specifications,
or other approved configuration documentation. These can be further defined as critical, major,
or minor.
Operational Unit Directorate (OUD). For purposes of this Manual only, the OUD consist of
the 5 regions DCMAE, DCMAC, DCMAW, DCMAS and DCMAI and oversee the CMOs
assigned to them.
Process Evaluation. Process Evaluation is a surveillance category that is used for conducting
surveillance of a system/subsystem/process (referred to as “process”). Process Evaluation must
be used when assessing Contractor Business Systems, quality systems, management systems or
processes (primarily at the multi-facility or facility level). It involves evaluating contractor
process adequacy, compliance, and outputs. Process evaluations may be conducted or executed
as a single review, on a recurring (e.g., weekly, monthly) interval, or on an ongoing basis for a
specified duration.
Subcontract. A contract entered into by a subcontractor to furnish supplies or services for
performance of a prime contract or a subcontract. It includes, but not limited to, purchase orders,
and changes and modifications to purchase orders.
Subcontractor. Any contractor, distributor, vendor, or firm that furnishes supplies or services to
or for a prime contractor or another subcontractor.
System of Record. The system of record is any system used to store data (i.e., WAWF, PIEE,
etc.).
DCMA-MAN 2101-01, March 24, 2019
Glossary Acronyms 29
G.2. ACRONYMS.
ACO Administrative Contracting Officer
APS Accountable Property System
ARP Alternative Release Procedure
CAO Contract Administration Office
CAR Corrective Action Request
CMO Contract Management Office
CoC Certificate of Conformance
COR Contracting Officer Representative
DD Form 1222 Request for and Results of Tests
DD Form 250 Material Inspection and Receiving Report
DFARS Defense Federal Acquisition Regulation Supplement
DLAD Defense Logistics Acquisition Directive
DoD Department of Defense
DPE Deliverables Product Evaluation
E&M Engineering and Manufacturing
FAR Federal Acquisition Regulation
FAT First Article Test
FLS First Level Supervisor
FLSR First Level Supervisor Review
FS Functional Specialist
FSM Functional Specialist Meeting
GCS Government Contract Surveillance
GMIP Government Mandatory Inspection Point
IAW In Accordance With
ID Identification
IUID Item Unique Identification
NASA National Aeronautics and Space Administration
OUD Operational Unit Directorate
PAOC Postaward Orientation Conference
PCO Procuring Contracting Officer
PE Process Evaluation
PIEE Procurement Integrated Enterprise Environment
PLT Production Lot Test
POP Place of Performance
PVT Production Verification Testing
DCMA-MAN 2101-01, March 24, 2019
Glossary Acronyms 30
QAE Quality Assurance Engineer
QA Quality Assurance
QAS Quality Assurance Specialist
RFID Radio Frequency Identification
RP&P Risk Profile & Plan
RR Receiving Report
RRR Repairables Receiving Report
SPDP Software Professional Development Program
TDA Enterprise Performance Advocacy Division
TDM Technical Directorate Manufacturing and Quality Division
WAWF Wide Area Workflow
DCMA-MAN 2101-01, March 24, 2019
REFERENCES 31
REFERENCES
DCMA Instruction 1206, “First Level Supervisory Reviews”
DCMA Manual 2101-04, “Delegate Surveillance
DCMA Manual 2301-06, “Discrepancy Processing
DCMA Manual 2301-1, "Contract Safety"
DCMA Manual 2303-04, “Surveillance - Document and Provide Feedback”
DCMA Manual 4201-09, “First Level Supervisory Reviews
DCMA Manual 4501-04 “Records Management
DFARS Appendix F, “Material Inspection and Receiving Report”
DFARS PGI 225.8, “Other International Agreements and Coordination”
DFARS 225.870, “Contracting with Canadian contractors”
DFARS 246.472, “Inspection Stamping”
DFARS Procedures, Guidance and Information, 246.472, “Inspection Stamping”
DFARS 246.471, “Authorizing Shipment of Supplies”
DFARS 246.504, “Certificate of Conformance”
DFARS 252.232-7003, “Electronic Submission and Processing of Payment Requests and
Receiving Reports”
DoD Directive 5105.64, “Defense Contract Management Agency (DCMA),” January 10, 2013
FAR 9.307, “Government Administration Procedures”
FAR Part 46, “Quality Assurance
FAR 46.407 “Nonconforming Supplies or Services”
FAR 46.406, “Foreign Governments”
FAR 46.408, “Single-Agency Assignments of Government Contract Quality Assurance”
FAR 46.505, “Transfer of Title and Risk of Loss”
FAR 52.209-3, “First Article Approval - Contractor Testing” "SEP 1989"
FAR 52.209-4, “First Article Approval - Government Testing” "SEP 1989"
FAR 52.246-2, “Inspection of Supplies - Fixed-Price” "AUG 1996"
FAR 52-246-3, “Inspection of Supplies - Cost-Reimbursement”
FAR 52-246-4, “Inspection of Services - Fixed-Price”
FAR 52-246-5, “Inspection of Services - Cost-Reimbursement”
FAR 52-246-6, “Inspection - Time-and-Material and Labor-Hour”
FAR 52-246-7, “Inspection of Research and Development - Fixed-Price”
FAR 52-246-8, “Inspection of Research and Development - Cost-Reimbursement”
FAR 52.246-15, “Certificate of Conformance” "APR 1984"
NASA Procedural Requirements 8735.2B, “Management of Government Quality Assurance
Functions for NASA,” August 12, 2013